York Road at Metra/CPKC grade separation
Summary
With the CPKC merger bringing longer, more frequent trains, delays at the York Road crossing are expected to get worse. The board locked in $1.5 million in state funding for Phase I engineering on an underpass.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
Village's remaining engineering share is about $397,800 after grants cover $2.5 million.
Drivers, emergency responders, and anyone stuck waiting at the York Road crossing.
Mentions & discussions (2)
Village Board of Trustees - Oct 27, 2026
With the CPKC merger bringing longer, more frequent trains, delays at the York Road crossing are expected to get worse. The board locked in $1.5 million in state funding for Phase I engineering on an underpass.
Village Board of Trustees - Jul 28, 2026
With CPKC trains growing longer and more frequent, the village's four at-grade crossings can Paralyze the town — including emergency response. The board committed roughly $2.9 million in Phase I engineering for an underpass, most of it covered by federal and state grants, toward a project estimated at $56.6 million.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bensenville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.