Civic Issues
Topics getting the most attention in Bensenville public meetings, ranked by how frequently they are discussed.
3 issues in roads with high priority
Evergreen Street Special Service Area
The special service area project came in under budget, so the village will use leftover bond money to pay off the bonds two years early, trimming interest and shortening the tax levy through 2041.
Industrial Drive Reconstruction
Five industrial streets — Entry, Bernice, James, Judson and Williams — get full rebuilds with new concrete roads, water mains, storm sewers, lighting and sidewalks. A $3 million state grant and a special service area on local property owners split the cost.
Foster Avenue Reconstruction STP Project
The Village is moving ahead on rebuilding Foster Avenue from Route 83 to York Road — new pavement, curbs, sidewalks, water mains and more — with an $8.47 million federal grant expected by July. Construction is targeted for 2031, but good design work now could move it up the list.