2025 Water Main Improvements Change Order
Summary
Public Works is repairing water mains and service leaks nearly daily to cut water loss, while prepping for spring and summer capital projects.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 12, 2026.
Impact analysis
The change order adds $55,156 to the contract, though total costs are expected to stay under the base contract value.
All village water customers benefit from reduced water loss and more reliable service.
Residents who didn't receive scheduling letters may face confusion or delays in arranging in-home access.
Mentions & discussions (4)
Village Board - 12 Oct 2026
The village continues replacing lead water service lines, with a $55,156 contract increase approved. Some Hollywood-area residents reported missing the letters to schedule in-home access work — staff promised to follow up.
Village Board - 13 Jul 2026
The water main project came in lower than expected — a change order cut the contract with Suburban General Construction by $353,393.55.
Village Board - 22 Jun 2026
Three change orders cut nearly a million dollars from the 2025 lead water service replacement contracts, because crews found fewer replacements than budgeted.
Village Board - 09 Feb 2026
Public Works is repairing water mains and service leaks nearly daily to cut water loss, while prepping for spring and summer capital projects.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Brookfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.