ApprovedConditional Use

Ameren Illinois Substation Expansion

Description

Ameren wants to expand its existing substation south of the Southern Illinois Airport to strengthen the grid. The council approved the special use permit with two conditions — annexation into the city and a compliant drainage system or retention pond.

Impact summary

The project upgrades aging grid infrastructure for better reliability, but neighbors worried about stormwater runoff into a drainage way serving roughly 825 acres.

Applicant

Name
Ameren Illinois Company
Address
1086 Airport Road

At a glance

Hearings
1
Public comments
1
Total mentions
1

Last vote · City Council

Approved7–0, unanimous

Last discussed Sep 8, 2026.