Structural Steel Bid Shortage and Bidding Waiver
Summary
No contractor bid on the structural steel package because data center projects are hoovering up steel and steelworkers. The Village solicited bids through unconventional means and included language letting the Board waive formal bidding rules to keep the project on schedule and budget.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 17, 2026.
Impact analysis
The steel package came in about $319,000 over estimate, but the overall project still ended about $1 million below the prior cost estimate.
The project stays on schedule and budget despite the steel market squeeze.