Water System Maintenance Contracts
Two consent items keep the water system humming: $50,432 for exercising water main valves so they work in emergencies, and a salt bid at $151.28 per ton for water softening.
Wastewater Treatment Plant State Award and Emergency Repairs
A $55,925 contract would modernize the computer controls (SCADA) at the wastewater treatment plant — the behind-the-scenes tech that keeps the sewer system running.
Integrated infrastructure master plan
The village now has a unified 10-year roadmap for roads, water, sewer, and stormwater so projects get done together instead of tearing up the same street twice. Road spending would jump from about $4.4 million to over $10 million a year to hit an excellent pavement score by 2031, and about $66 million in projects hinge on low-interest state loans.