Alfresco Alley Streetscape Phase II Cost Increase

Summary

The downtown project is now about $570,000 over the original budget because of substantial utility work, shade structure foundations and electrical costs; the decking was cut as an alternate. Cables will not be buried downtown — that would add millions.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Apr 7, 2026.

Impact analysis

💰Financial impact

About $570,000 over the original March estimate, absorbed within the budget via the capital transfer.

✅Who benefits

Downtown visitors and businesses once the streetscape is built.