Wastewater digester improvements
Summary
The village hired IHC Construction to replace aging aeration equipment and slide gates at the wastewater plant for up to $1.4 million including contingency — essential infrastructure upkeep for sewer service.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Total project budget of $1,403,050 including a 10% contingency.
All residents connected to village sewer service.
Mentions & discussions (2)
Village Board of Trustees Meetings - Oct 6, 2026
The village hired IHC Construction to replace aging aeration equipment and slide gates at the wastewater plant for up to $1.4 million including contingency — essential infrastructure upkeep for sewer service.
Village Board of Trustees Meetings - Sep 1, 2026
The village is moving forward with design work on its aging digester system — boiler, roof, flare controls, and digester cleaning — and may apply for a low-interest IEPA state loan to fund construction.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Cary
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.