High PriorityDevelopmentopen

ComEd KARE transmission substation at Keslinger and Crego Roads

Summary

ComEd plans a 345/138kV electrical substation on 160 acres it owns at the northeast corner of Keslinger and Crego Roads as part of its Kishwaukee Area Reliability Expansion. The utility withdrew its local rezoning request after getting state certification, but the land still has to be annexed into DeKalb via an agreement the City Council will review — the city's last real chance to set conditions on drainage, setbacks, and screening.

At a glance

Total mentions
3
Last 30 days
0

Last discussed Aug 24, 2026.