ComEd KARE transmission substation at Keslinger and Crego Roads
Summary
ComEd plans a 345/138kV electrical substation on 160 acres it owns at the northeast corner of Keslinger and Crego Roads as part of its Kishwaukee Area Reliability Expansion. The utility withdrew its local rezoning request after getting state certification, but the land still has to be annexed into DeKalb via an agreement the City Council will review — the city's last real chance to set conditions on drainage, setbacks, and screening.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 24, 2026.
Impact analysis
No direct city cost was discussed, but the project shapes future utility reliability and how the site is built out.
County-wide electric customers get upgraded transmission capacity, and nearby landowners benefit from a large retention pond improving drainage.
Neighbors lost their chance to formally object through the local rezoning hearing, though the annexation process remains open.
Mentions & discussions (2)
City Council (Regular) - Aug 24, 2026
The city annexed 160 acres where ComEd will build a transmission substation to power growth across DeKalb County — data centers, NIU, manufacturers. Residents questioned fee waivers and rate impacts; the council weighed tax revenue and a seat at the table against ComEd's right to build anyway under state approval.
Planning & Zoning Commission - Aug 17, 2026
ComEd plans a 345/138kV electrical substation on 160 acres it owns at the northeast corner of Keslinger and Crego Roads as part of its Kishwaukee Area Reliability Expansion. The utility withdrew its local rezoning request after getting state certification, but the land still has to be annexed into DeKalb via an agreement the City Council will review — the city's last real chance to set conditions on drainage, setbacks, and screening.
Related development
ComEd KARE Substation Annexation (11275 Keslinger Road)
Brings reliable regional power for data centers, NIU and manufacturers, adds property tax revenue for local taxing bodies, but leaves a downstream drainage dispute unresolved.
ComEd Keslinger Substation / KARE Project
The substation and accessory uses will take up roughly 55% of the site, with a laydown yard and a large retention pond on the south end draining toward the Kishwaukee River; annexation terms now go to the City Council.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for DeKalb
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.