Elmhurst Quarry flood control facility repairs
Summary
A $188,658 contract with V3 Construction Group will repair the Kress Creek upstream weir, with work running through 2030.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Contract total not to exceed $188,658.
Kress Creek watershed residents who rely on the weir for flood control.
Mentions & discussions (2)
Stormwater Management Committee โ October 6, 2026
A $188,658 contract with V3 Construction Group will repair the Kress Creek upstream weir, with work running through 2030.
DuPage County Board โ March 10, 2026
The county is putting serious money into its 30-year-old Elmhurst Quarry flood control facility โ a $5.87 million appropriation plus engineering and a $5.78 million construction contract to stabilize the quarry's rock highwall and keep the flood protection working.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for DuPage County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.