Engineers found a hydraulic bottleneck limiting the regional wastewater treatment plant's tertiary filters. A $66,600 study will figure out how to fix it before capacity problems grow.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
Up to $66,600 for the engineering study.
All sewage customers served by the regional plant.
Mentions & discussions (2)
Village of Frankfort Board — October 5, 2026
Engineers found a hydraulic bottleneck limiting the regional wastewater treatment plant's tertiary filters. A $66,600 study will figure out how to fix it before capacity problems grow.
Village of Frankfort Board — May 18, 2026
The village is fixing 154 manholes with inflow and infiltration problems and continuing a sewer evaluation survey in the Heritage Knolls, Founders Place and Vans Drive areas. Total project cost is estimated around $545,000, funded in the 2026-27 budget.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Frankfort
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.