Civic Issues
Topics getting the most attention in Geneva public meetings, ranked by how frequently they are discussed.
3 issues in water utilities with high priority
Integrated infrastructure master plan and rate study
The city is spending $485,294 on a combined pavement, water, sewer, and water-modeling study to better sequence capital projects for the next 30 years — and the rate study will feed into future water and sewer rate decisions.
East State Street lead water service replacements
In committee of the whole, aldermen endorsed a $324,360 contract with IHC Construction to replace up to 20 lead and galvanized water services on East State Street as part of the reconstruction.
Sanitary river crossing and screening building change orders
The council gave the city administrator authority to approve up to $1.06 million in combined change orders on two wastewater projects, so construction doesn't stall waiting for council approval. Work includes coffer dams on the Fox River starting this summer.