Wastewater Treatment Plant UV Disinfection Conversion
Summary
The 45-year-old sludge building has only about five years of life left, so the village is accelerating $1.6 million in engineering now. A $1.87 million UV disinfection project was also moved up to save mobilization costs and reduce chlorine storage.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 12, 2026.
Impact analysis
About $1.87 million for UV plus $1.6 million engineering over two years, drawn from environmental fund reserves.
Everyone on village water and sewer gets more reliable treatment infrastructure.
Mentions & discussions (3)
Special Village Board — November 12, 2026
The 45-year-old sludge building has only about five years of life left, so the village is accelerating $1.6 million in engineering now. A $1.87 million UV disinfection project was also moved up to save mobilization costs and reduce chlorine storage.
Village Board Meeting (No COW) — July 16, 2026
The board approved a contract to convert the wastewater treatment plant to UV disinfection, a major piece of utility infrastructure work.
Special Village Board — April 7, 2026
The plant will replace its 2,000-pound chlorine stockpile — stored next to a school — with a UV disinfection system, a long-planned safety improvement funded with a $185,000 DCEO grant.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Glendale Heights
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.