Commercial solar development in Grundy County
Summary
Two large solar projects got their special use permits extended a year, through March 2027, so permitting and construction can wrap up. The developer has signed grid agreements with ComEd, closed financing, and expects to start building in spring 2026.
At a glance
- Total mentions
- 18
- Last 30 days
- 0
Discussed at 2 meetings in the last 60 days; most recently Oct 13, 2026.
Impact analysis
The developer has roughly $900,000 committed in interconnection deposits alone, with construction spending to follow in the county.
The county gains renewable energy development, lease revenue for landowners, and construction activity starting in 2026.
Neighboring landowners worry about home values; Laura Schiavone argued the value study downplayed risks.
Mentions & discussions (18)
County Board - Regular Meeting — October 13, 2026
A 6.8 MW commercial solar project on the Wills family's 160-acre farm passed 7-5. Supporters cited retirement security for the farm family; critics questioned the property value study and who ultimately profits from the project.
Land Use Committee/ - Regular Meeting — September 23, 2026
Four solar projects moved forward this meeting, and Grundy County remains a prime target for solar and battery development because of its farmland and transmission access. The Sunrise Mountain project on largely non-prime, flood-prone farmland drew the only split vote.
Zoning Board of Appeals Committee - Regular Meeting — September 15, 2026
A 6.8-megawatt solar array on 53 acres of the Wills family farm would power about 1,300 homes with a 10% bill discount and bring roughly $900,000 in tax revenue over 40 years. It was tabled in August over decommissioning and sourcing issues, now fixed.
Zoning Board of Appeals Committee - Regular Meeting — August 18, 2026
The large solar project nears a decision but was tabled one month because staff received a key document submittal too late to review. Residents who came to comment must return September 15.
County Board - Regular Meeting — August 11, 2026
The board approved letting a local farmer cut alfalfa between the rows of the Gillard Solar array — an early commercial example of combining farming with utility-scale solar. Supporters like the dual-use idea; board member Laura Schiavone warned it removed 205 acres of prime corn and soybean ground and shouldn't be mistaken for farmland preservation.
Land Use Committee/ - Regular Meeting — July 22, 2026
Gillard Solar wants to lease 25 acres of its array to a local hay farmer instead of planting pollinator ground — returning farmland to production but raising fire-risk questions since there's no water on site. It could also set a precedent for how agrivoltaics work on future solar farms countywide.
Zoning Board of Appeals Committee - Regular Meeting — July 21, 2026
Approving hay agrivoltaics here could shape how all future solar farms handle agriculture in Grundy County. Staff worried about fire risk on a site generating electricity with no water supply; the developer countered with a $30,000 fire ATV for the local fire district and argued the alternative — unmowed dry grass — is riskier.
Grundy County Insurance Trust - Regular Meeting — July 14, 2026
A new lawsuit alleges the county improperly extended a special use permit for the Goose Lake Solar project after it expired. Solar cases are now believed to number seven or more, and while they don't carry big dollar payouts, the legal defense costs are driving up the trust's losses.
Land Use Committee/ - Regular Meeting — June 24, 2026
Solar developers keep sending inquiries even with the county's battery storage moratorium running 120 days after June 1. No data center or battery projects are currently being prepared for the county board.
County Board - Regular Meeting — June 9, 2026
The state gave counties until June 26 to update renewable siting rules or fall back to weak state minimums. Grundy adopted tougher-than-state rules requiring final drainage, road and decommissioning plans upfront. It's a big deal for anyone near proposed solar farms — five projects are already waiting.
Land Use Committee/ - Regular Meeting — May 27, 2026
State law forced counties to update renewable energy siting rules by June 2026, but Grundy County used the rewrite to lock in the toughest protections allowed: drainage and drain tile surveys, road damage guarantees, emergency communications studies, wildlife and glare studies, and strong decommissioning bonds. About six solar developments are waiting on this ordinance.
Zoning Board of Appeals Committee - Regular Meeting — May 19, 2026
A new state law forces counties to update renewable energy siting rules by June 2026. Grundy's rewrite demands more upfront information, road and drainage protection, wildlife studies, and decommissioning funds — while critics say it still lacks due process safeguards.
County Board - Regular Meeting — May 12, 2026
The board unanimously backed SB3450, which would give counties back a say in where utility-scale solar farms are built. Members said current state rules let solar projects box in towns and block planned growth.
Education/Personnel/VAC - Regular Meeting — April 9, 2026
Board member Harold Vota flagged broken solar panels at the Gardner facility sitting unrepaired for months and wants county hires to inspect sites — possibly by drone — and strip special-use permits when operators don't fix panels quickly.
Land Use Committee/ - Regular Meeting — March 25, 2026
The solar project got a one-year extension so the developer can finish engineering and pull building permits — all 30 original conditions stay in place. Laura Schiavone was the lone no vote.
Land Use Committee/ - Regular Meeting — February 25, 2026
Two large solar projects got their special use permits extended a year, through March 2027, so permitting and construction can wrap up. The developer has signed grid agreements with ComEd, closed financing, and expects to start building in spring 2026.
Zoning Board of Appeals Committee - Regular Meeting — February 17, 2026
The county's attempt to clarify its solar farm code requirements is delayed again so comments can be addressed. It won't come back until May 19, 2026.
Zoning Board of Appeals Committee - Regular Meeting — January 20, 2026
A text amendment to clarify solar farm code requirements for special use was set to be heard but the petitioner asked for a delay. It will come back February 17.
Related development
UDO Text Amendment
Developers and homeowners will see clearer permit steps, required pre-application meetings, and new grading/survey requirements across unincorporated Grundy County.
Goose Lake Township Solar 1 LLC — special use extension (26 ZBA 014)
The project is construction-ready and can move forward into the next fiscal year.
Text Amendment to Clarify Solar Farm Code Requirements for Special Use
The rules governing solar farm special uses in the county remain unchanged for now.
26-ZBA-004 Text Amendment — Wind Ordinance
Same heightened protections for wind projects — roads, drainage, decommissioning funds — before the June 26 deadline.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Grundy County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.