Gorman Road Full-Depth Reclamation Extra Work Costs
Summary
The nearly finished Gorman Road project ran about $300,000 over, mostly because of surprise field tiles and utility relocations; the board approved $160,000 in local highway funds to cover it.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
$160,000 from general highway funds on top of motor fuel tax funding.
Drivers who use Gorman Road get a fully rebuilt road.
County highway fund reserves take a $160,000 hit that wasn't budgeted.
Mentions & discussions (2)
County Board - Regular Meeting — October 13, 2026
The nearly finished Gorman Road project ran about $300,000 over, mostly because of surprise field tiles and utility relocations; the board approved $160,000 in local highway funds to cover it.
Animal Control/Highway/Transit Committee - Regular Meeting — September 17, 2026
The Gorman Road full-depth reclamation project ran into unforeseen conditions, and finishing it will take an extra $160,000 out of county highway funds. The full board will vote October 13.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Grundy County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.