Rice Road Bridge delay to Spring 2027
Summary
The Rice Road Bridge replacement goes to bid the day after the meeting. It's a full tear-down and rebuild — the old bridge sits in clay with deteriorated outside beams — expected to take an entire construction season and roughly $3 million, with no good detour while it's closed.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 22, 2026.
Impact analysis
Engineers estimate roughly $3 million for the replacement.
Rice Road travelers, who get a safe new bridge instead of a scour-critical structure.
Residents near the bridge will face a season-long closure with a lengthy detour.
Mentions & discussions (3)
Animal Control/Highway/Transit Committee - Regular Meeting — October 22, 2026
The Rice Road bridge project is waiting on ComEd and NICOR to relocate utilities before demolition can begin — permits are in hand and the utility companies are engaged.
Animal Control/Highway/Transit Committee - Regular Meeting — July 23, 2026
The Rice Road Bridge rebuild won't start this year — a Nicor gas main still needs to move and steel and beam lead times are too long to finish before winter. One shoulder is closed now; the county wants to avoid closing the bridge all winter.
Animal Control/Highway/Transit Committee - Regular Meeting — April 23, 2026
The Rice Road Bridge replacement goes to bid the day after the meeting. It's a full tear-down and rebuild — the old bridge sits in clay with deteriorated outside beams — expected to take an entire construction season and roughly $3 million, with no good detour while it's closed.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Grundy County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.