Civic Issues
Topics getting the most attention in Hanover Park public meetings, ranked by how frequently they are discussed.
7 issues in roads
Lake Street planter bed repairs
A $79,000 no-bid contract with Martam Construction would fix two damaged concrete planter beds along Lake Street, a key commercial corridor.
2026 Street Resurfacing and Pavement Maintenance
Chicagoland Paving got a $155,000 contract (plus up to $15,500 contingency) for the 2026 pavement maintenance in the Greenbrook Tanglewood special service area.
Commuter lot sustainability
The commuter parking lot fund is running on fumes — about $200 expected in fund balance — because post-COVID ridership hasn't recovered. The village stopped subsidizing it and restructured staffing to save about $150,000 a year.
2026 Arterial Fence Program
The village awarded a $145,000 contract to Fence Connection, Inc. to repair and replace fencing along Irving Park Road and Barrington Road, including storm-damaged sections, plus spot repairs village-wide.
Arlington Drive Bridge reopens
Interim Manager Sage announced the Arlington Drive Bridge is now open, with a construction video already drawing over a thousand views online.
Recurring Church Street flooding
Brian and Michelle Seiver say Church Street flooded again this week, damaging cars and homes, two years after first raising it. Staff says the fix depends on an infrastructure project not yet underway, and overnight pumping helped drain the road.
Delayed roadway projects — County Farm Road Trail and Irving Park lighting
A $25,242.76 supplement to the Ciorba Group engineering contract moves the Irving Park Road lighting project forward, now totaling $74,836.76 in engineering costs.