Medium PriorityDevelopmentopen

NOW Arena kitchen and concession flooring replacement

Summary

The arena's original 2006 epoxy flooring in kitchen and concession areas has delaminated and cracked, making it hard to clean and putting the village at risk of health code issues. The fix will cost up to $165,210, with only one company bidding.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 22, 2026.

Impact analysis

💰Financial impact

Costs up to $165,210, about $15,210 more than budgeted, with the difference coming from fund reserves.

✅Who benefits

Arena visitors get a cleaner, code-compliant food service operation; the village avoids bigger repair bills later.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Hoffman Estates

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.