ComEd Substation Expansion
Summary
ComEd wants to modernize its aging Bell Road substation with two new buildings, the tallest nearly 59 feet — which would make it the tallest structure in Homer Glen and requires a pile of zoning exceptions. The commission recommended it 4-1 with conditions covering the security wall extension, landscaping maintenance, and township approvals. The Village Board makes the final call, possibly July 22.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Discussed at 2 meetings in the last 60 days; most recently Oct 14, 2026.
Impact analysis
Ratepayers and the community benefit from improved electric reliability; the cost is borne by ComEd, though residents near Bell Road face potential visual and resale impacts.
Homer Glen residents and businesses get a more reliable, resilient power supply as the community grows, plus a public rest area with a butterfly garden.
Homes on the east side of Bell Road will face a much taller neighbor — Commissioner Stanly warned of sunset blockage and resale concerns for roughly 30 houses.
Mentions & discussions (4)
Village Board - Oct 14, 2026
The most contentious item in Homer Glen right now: ComEd wants to replace its aging 70-year-old open-air substation with a gas-insulated facility inside a 58'8" building. Trustees fought over height, setbacks, EMF health risks, and what residents get in return, ultimately approving it 4-2 only after adding a $500K–$1.5M beautification condition.
Village Board - Sep 23, 2026
ComEd wants to build a large weather-protected enclosure housing gas-insulated switchgear at its 70-year-old substation on Bell Road, replacing equipment past its 40-year life. Trustees pressed on what Homer Glen residents actually gain, why there's no site-specific EMF study, and whether data centers are driving the capacity — then tabled it for ComEd's full team to answer.
Plan Commission - Jul 2, 2026
ComEd wants to modernize its aging Bell Road substation with two new buildings, the tallest nearly 59 feet — which would make it the tallest structure in Homer Glen and requires a pile of zoning exceptions. The commission recommended it 4-1 with conditions covering the security wall extension, landscaping maintenance, and township approvals. The Village Board makes the final call, possibly July 22.
Plan Commission - Jun 18, 2026
ComEd wants to replace its aging Bell Road substation with a modern, weather-protected enclosed facility, cutting power outages and supporting growth. Neighbors mostly support it, but the commission wants answers on parking, lighting, and the security wall before voting.
Related development
ComEd Substation Special Use and PUD
Reliability improves for the growing community, but the Village's tallest building rises on Bell Road — with landscaping conditions and a wall extension to soften the view.
ComEd Substation Expansion (Goodings Grove)
A more reliable electric grid and trail/landscaping improvements, but the commission flagged parking waivers, the tall wall, and construction staging on Township property as open items.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Homer Glen
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.