Heritage Park Phase One — veterans memorial and water feature
Summary
Two items touch Heritage Park: design work for the Veteran's Memorial and Water Feature, and an insurance waiver so K Brothers Fence can work on the tennis and pickleball courts.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 12, 2026.
Impact analysis
About $9,370.50 in design services plus a contractor whose $1M excess liability coverage would be waived.
Park users, veterans, and tennis and pickleball players.
Mentions & discussions (4)
Village Board (Special) - Nov 12, 2026
Two items touch Heritage Park: design work for the Veteran's Memorial and Water Feature, and an insurance waiver so K Brothers Fence can work on the tennis and pickleball courts.
Village Board - Mar 11, 2026
The village is moving ahead with Phase II of Heritage Park, approving $5,750 for soil testing as part of final engineering. Phase One is on schedule, with the village hunting grants to lower costs.
Village Board - Feb 25, 2026
American Legion Post 2011 recognized Marian Village, EXI Inc., State Farm, Judge Art Smigielski, and Linda McCluskey for supporting local veterans.
Village Board - Jan 14, 2026
The Lakota Group showed off the final design for the park's first phase: a veterans memorial with a fallen soldier sculpture, an interactive water feature, and a 65-foot pavilion with restrooms. Bidding starts in April, and veterans who attended endorsed the design.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Homer Glen
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.