Recommended approval (Apr 2026) · Council outcome not on recordRezone

Metra/ComEd Traction Power Substation and Transformer Facility

Description

Metra wants to rezone about 5.34 acres to PL-2 and get a special use permit and site plan approval for a small unoccupied electrical substation with a fenced transformer yard near the Metra station.

Impact summary

Construction could start by September 2026 and finish around early 2028, taking five commuter lot spaces and possibly overlapping with viaduct work — expect some short-term traffic and parking impacts downtown.

Applicant

Name
Metra / Hatch Consultants Ltd. / GFT Inc.
Address
18277 Park Avenue, Homewood, ILSee this on the map

At a glance

Hearings
1
Public comments
0
Total mentions
1

Last vote · Planning Commission

Recommended approval (Apr 2026) · Council outcome not on record5–0

A recommendation. The council’s outcome is not on record here.

Last discussed Apr 23, 2026.

We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.

The weekly brief for Homewood

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.