Aldi-funded Kirk Road/Douglas Road intersection project
Summary
About $1.87 million in contracts to repave Dundee, Hampshire and Kaneville townships and patch concrete on Kirk Road between Route 64 and 38 — townships pay for their own work but KDOT bids it cheaper.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Feb 17, 2026.
Impact analysis
$1,158,960.53 for Kirk Road plus $717,043.15 in township contracts (township-funded).
Drivers on Kirk Road and residents of the three townships.
Mentions & discussions (2)
KC Transportation Committee — February 17, 2026
About $1.87 million in contracts to repave Dundee, Hampshire and Kaneville townships and patch concrete on Kirk Road between Route 64 and 38 — townships pay for their own work but KDOT bids it cheaper.
KC Transportation Committee — January 20, 2026
Aldi is paying the full tab — design, construction, and now $194,905.78 in Phase III engineering through WBK Engineering — for the Kirk Road at Douglas Road intersection improvement. No county funds are involved, though the committee debated whether an appropriation clause was still needed.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Kane County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.