Buffalo Creek Wetland Mitigation Bank monitoring
Summary
The wetland bank near Buffalo Creek needs up to two more years of monitoring because drought years have delayed federal approval. A $40,500 change order keeps the project compliant with Army Corps of Engineers standards.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 6, 2026.
Impact analysis
$40,500 change order plus $29,500 supplemental appropriation; cumulative change orders now total $76,000, a 35.6% increase.