Summary
The board approved a $1.76 million engineering contract plus $2.1 million in sales tax funds, along with agreements with Round Lake Beach, Round Lake Park, and Avon Township, to improve Hainesville Road from Washington Street to Rollins Road with sidewalks and multi-use paths.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 11, 2026.
Impact analysis
About $2.1 million in quarter-percent transportation sales tax is being appropriated, with engineering capped at $1.76 million.
Drivers, pedestrians, and cyclists traveling through the Round Lake area corridor.
Travelers may face construction delays.
Mentions & discussions (3)
Lake County Board — August 11, 2026
The board approved a $1.76 million engineering contract plus $2.1 million in sales tax funds, along with agreements with Round Lake Beach, Round Lake Park, and Avon Township, to improve Hainesville Road from Washington Street to Rollins Road with sidewalks and multi-use paths.
Financial & Administrative Committee — August 6, 2026
A bundle of agreements with Round Lake Beach, Round Lake Park, Avon Township, and engineer Baxter & Woodman moves the Hainesville Road rebuild from Washington Street to Rollins Road forward, backed by over $2.1 million in transportation sales tax funds.
Lake County Board — February 10, 2026
The board hired Stanley Consultants for Phase I engineering on this long-planned intersection upgrade, funded by the quarter-percent transportation sales tax. Construction is still downstream, but the design work now has a price and a contractor.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lake County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.