Downtown courthouse backup generator
Summary
Ottawa's mayor came in person to defuse the fight over backup power at the downtown courthouse. The city agrees the basement transformers should move but says the proposed 200-kilowatt generator is oversized for its stated safety purpose and needs Historic Preservation Committee approval before any permit.
At a glance
- Total mentions
- 7
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 25, 2026.
Impact analysis
The generator's cost wasn't stated, but board members noted rerouting lines to a remote lot would add significant conduit and digging expense.
A compromise would keep courthouse staff, jurors and visitors safe during outages while preserving Ottawa's historic downtown character.
Until it's resolved, a power failure could trap people in courthouse elevators and leave courtrooms dark, and the backlog of sensitive court cases grows with each shutdown.
Mentions & discussions (7)
County Property Committee - Sep 25, 2026
The committee revisited whether the planned downtown generator should burn diesel or natural gas. They landed on diesel — it's smaller, works if gas supply fails, and Illinois may restrict gas appliances — but the county still needs City of Ottawa's approval and is still waiting on a grant notification before bidding.
County Property Committee - Aug 14, 2026
The $500,000 downtown courthouse generator project is waiting on a FEMA hazard mitigation grant that's listed as funded but not awarded. The committee agreed to wait rather than bid now, which could cost reimbursement eligibility — though the project has been delayed 15 years already.
County Property Committee - Jul 24, 2026
The county's generator grant application was passed over initially, but Springfield officials say Cook County's withdrawal frees up funds the county would likely receive. The catch: purchasing or starting construction on the generator could void the roughly $520,000 grant. The committee plans to solicit bids but hold them unopened for about 90 days while awaiting the grant decision.
County Property Committee - Jun 26, 2026
Chairman Jensen proposes placing the new generator on the courthouse's south lawn so it echoes the building's columned facade and avoids blocking windows. It needs new drawings and sign-off from the mayor and historical society before bids go out.
County Property Committee - May 22, 2026
Years in the making, the generator would keep the whole downtown courthouse — and the courts that depend on its servers — running in an outage. Removing Ameren's transformers requires a new electrical service estimated around $250,000, and the committee agreed to send the whole project to the full board to go out for bid, possibly with alternate bids for two locations.
County Board - May 14, 2026
Ottawa's mayor came in person to defuse the fight over backup power at the downtown courthouse. The city agrees the basement transformers should move but says the proposed 200-kilowatt generator is oversized for its stated safety purpose and needs Historic Preservation Committee approval before any permit.
County Property Committee - Apr 24, 2026
The long-running plan to install a backup generator at the downtown courthouse remains hung up on the City of Ottawa's letter of appropriateness. Members discussed safety concerns for courthouse employees, moving Ameren transformers, and possibly hiring their own electrical engineer.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for LaSalle County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.