Downtown courthouse generator project stalled
Summary
The county unveiled designs to screen the new courthouse generator with block pilasters and cedar fencing. The committee leaned toward the south-side spot, though one option could interfere with a photo spot near the courthouse — the design now goes to the City of Ottawa for approval.
At a glance
- Total mentions
- 6
- Last 30 days
- 2
Rising — discussed at 3 meetings since Oct 5, 2026, up from 0 in the two months before.
Impact analysis
Costs aren't finalized; placing the enclosure east could save a bit on wiring, and bids may go out next month.
Courthouse operations get reliable backup power, and the enclosure design keeps the courthouse's historic appearance intact for visitors and photographers.
Everyone working in and visiting the unsprinklered downtown courthouse remains at risk the longer it's delayed.
Mentions & discussions (6)
County Property Committee - Nov 13, 2026
The county unveiled designs to screen the new courthouse generator with block pilasters and cedar fencing. The committee leaned toward the south-side spot, though one option could interfere with a photo spot near the courthouse — the design now goes to the City of Ottawa for approval.
County Property Committee - Oct 23, 2026
The backup generator for the downtown courthouse is still waiting on IMEG engineering drawings, pushing the bid timeline into November at the earliest. Members set a deadline for plans at the next meeting; the full board previously voted to move forward even if the City of Ottawa objects.
Finance & Fee Committee - Oct 5, 2026
The $735,000 courthouse generator replacement, previously listed for 2028, was moved to 2033 in the capital plan, with a possible grant that could lower the cost.
County Property Committee - Jul 10, 2026
The full board already voted to go out to bid for the downtown generator, but bids haven't gone out while revised drawings are awaited. Chairman Jensen pushed to separate the generator purchase bid from the installation project so the long-lead-time equipment can be ordered now.
County Board - Jun 8, 2026
After years of waiting, the board authorized bidding for a backup generator at the downtown courthouse. Members discussed pursuing FEMA grant money, and the State's Attorney confirmed bidding is required no matter how it's funded.
County Property Committee - May 8, 2026
The long-delayed backup generator for the downtown Ottawa courthouse is still stuck in the permitting dance with the city — the historical society rejected it first, and the county is cooperating to avoid litigation. Joe Savitch called the courthouse a 'ticking time bomb' with no fire suppression, and the Ottawa mayor may address the full board next week.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for LaSalle County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.