The courthouse's electrical transformers sit in a cramped, hazardous basement and are grandfathered out of current Ameren standards. Ameren will move them if the county picks and prepares a new site — likely the south lawn — paying for conduit, wiring, and metering, possibly in spring 2027.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Aug 28, 2026.

Impact analysis

💰Financial impact

The county added $735,000 to next year's budget to cover the transformer move and generator work — and some members worry that won't be enough.

✅Who benefits

Courthouse staff and visitors get safer, more reliable power — and so does the rest of the grid on Ottawa's east side.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for LaSalle County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.