Four-pipe conversion may run over budget

Summary

The design behind the governmental center needed three smaller chiller units instead of two, adding piping, valves and electrical work. With about $950,000 plus 10% contingency budgeted, bids opening August 14 will show whether extra money is needed at budget time.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 10, 2026.

Impact analysis

💰Financial impact

About $950,000 budgeted now; the third chiller unit could push the final cost higher.

✅Who benefits

County buildings get modern, efficient heating and cooling.

⚠️Who could be affected

Taxpayers could shoulder a supplemental appropriation if bids come in over budget.