Four-pipe conversion may run over budget
Summary
The design behind the governmental center needed three smaller chiller units instead of two, adding piping, valves and electrical work. With about $950,000 plus 10% contingency budgeted, bids opening August 14 will show whether extra money is needed at budget time.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 10, 2026.
Impact analysis
About $950,000 budgeted now; the third chiller unit could push the final cost higher.
County buildings get modern, efficient heating and cooling.
Taxpayers could shoulder a supplemental appropriation if bids come in over budget.