Three buildings on 7th Street come down starting late April to make way for Moline's new central fire station. Demolition should wrap by early summer.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Aug 18, 2026.
Impact analysis
$450,245 from the capital budget.
Residents get a new central fire station and faster emergency response.
Mentions & discussions (5)
Committee-of-the-Whole Agenda & Council - Aug 18, 2026
The council approved the contract amendment that takes the new Central Fire Station design from 40% to 100% complete, with bidding this winter and construction starting spring 2027. The station may also serve as the city's first emergency 'resiliency hub.'
Committee-of-the-Whole Agenda & Council - Jun 23, 2026
The city hired Bush Construction to manage the new central fire station build with a guaranteed maximum price, giving taxpayers cost certainty before bonds are issued.
Committee-of-the-Whole Agenda & Council - May 12, 2026
The new fire station is at 40% design drawings, buildings on the Seventh Street site are being demolished, and a construction manager at risk will come before the council soon, with construction targeted to start in June.
Committee-of-the-Whole Agenda & Council - Mar 24, 2026
Three buildings on 7th Street come down starting late April to make way for Moline's new central fire station. Demolition should wrap by early summer.
Moline approves land purchase for new fire station to replace aging facility
Moline approves land purchase for new fire station to replace aging facility WQAD
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Moline
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.