South Slope WWTP improvements

Summary

The $114 million sewage treatment rebuild is 25% done, on schedule, with change orders at just 0.5% of the contract. The old activated sludge plant is offline and the RBC plant is carrying the load through a wet summer; completion is due November 2029.