South Slope WWTP improvements
Summary
The $114 million sewage treatment rebuild is 25% done, on schedule, with change orders at just 0.5% of the contract. The old activated sludge plant is offline and the RBC plant is carrying the load through a wet summer; completion is due November 2029.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
Change orders are only about $600,000 on a $114 million contract - well within the IEPA loan's allowance.
All Moline sewer customers get a modern, EPA-compliant treatment plant.
Sewer customers face compounding 6% annual rate increases.
Mentions & discussions (3)
Committee-of-the-Whole Agenda & Council - Oct 13, 2026
The $114 million sewage treatment rebuild is 25% done, on schedule, with change orders at just 0.5% of the contract. The old activated sludge plant is offline and the RBC plant is carrying the load through a wet summer; completion is due November 2029.
Committee-of-the-Whole - Jul 14, 2026
The $132 million South Slope wastewater project is on track for November 2029 completion, funded by a $120 million state loan at 1.96% interest. Sewer rates rise 6% a year to pay for it.
Committee-of-the-Whole Agenda & Council - May 12, 2026
The city's biggest project — a full rebuild of the South Slope wastewater treatment plant — is about 15% complete and on budget at $114.3 million. Phase 2 starts in 2027, with substantial completion expected August 31, 2029. Quarterly updates will now come to the council.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Moline
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.