Spring 2027 bonding for riverfront and fire station
Summary
Council gave staff the green light to plan for spring 2027 bonding: $10 million for riverfront redevelopment and $27 million for the new fire station. Formal resolutions will come back before any bonds are issued.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 22, 2026.
Impact analysis
$37 million in potential bonding; $23.75 million for capital projects over 10 years.
Downtown redevelopment and fire protection citywide.
Mentions & discussions (2)
Committee-of-the-Whole - Sep 22, 2026
Council gave staff the green light to plan for spring 2027 bonding: $10 million for riverfront redevelopment and $27 million for the new fire station. Formal resolutions will come back before any bonds are issued.
Committee-of-the-Whole Agenda & Council - May 12, 2026
The new fire station is at 40% design drawings, buildings on the Seventh Street site are being demolished, and a construction manager at risk will come before the council soon, with construction targeted to start in June.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Moline
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.