Riverwalk South Extension & Hillside Gateway

Summary

The commission is being asked to recommend adding a bid alternate to these major Riverwalk projects, with modifications from the Planning, Design, and Construction Committee. This shapes how the Riverwalk expands and connects for years to come.

At a glance

Total mentions
9
Last 30 days
3

Rising — discussed at 5 meetings since Sep 21, 2026, up from 3 in the two months before.

Impact analysis

💰Financial impact

The cost impact depends on whether the bid alternate is ultimately accepted when bids come in.

✅Who benefits

Riverwalk users and nearby neighborhoods would benefit from an expanded and improved trail and gateway experience.

⚠️Who could be affected

Taxpayers could bear additional costs if the full scope proceeds without matching outside funding.

Mentions & discussions (8)

MeetingNov 10, 2026

Riverwalk Commission — November 10, 2026

The commission is being asked to recommend adding a bid alternate to these major Riverwalk projects, with modifications from the Planning, Design, and Construction Committee. This shapes how the Riverwalk expands and connects for years to come.

MeetingNov 2, 2026

Riverwalk Planning, Design and Construction Committee — November 2, 2026

The committee is starting to scope out the Riverwalk South Extension and Hillside Gateway projects, which will shape how the Riverwalk extends south and how people enter the area. The discussion covers what the projects should include and what they might cost before any construction decisions are made.

MeetingOct 27, 2026

City Council — October 27, 2026

A resident challenged the $6.8 million River Walk South extension in the budget, calling it a want, not a need, and noting taxpayers haven't met fundraising goals.

MeetingOct 14, 2026

Riverwalk Commission — October 14, 2026

The South Extension's construction estimate jumped from $3 million to about $6.8 million, forcing the commission to weigh scaled-back alternatives. It voted to keep the full path connection from Hillside Road to Martin Avenue, sending cost details to a November PDC Committee meeting.

MeetingSep 21, 2026

City Council — September 21, 2026

The Riverwalk Commission is pushing for $6.8 million to fund the South Extension and Hillside Gateway project. Council members and former commissioners discussed rising project costs, private donations, and project scope.

MeetingSep 1, 2026

Riverwalk Planning, Design and Construction Committee — September 1, 2026

Resident Mary Lou Wehrli shared detailed ideas for the Eagle Street South Bank project, including renaming it "Quarry Bank," preserving the historic stone abutment and overlook stairs, and adding an ADA-accessible path.

MeetingAug 12, 2026approved

Riverwalk Commission — August 12, 2026

The new North Central College Riverwalk Park is under active construction, with completion expected October 30, 2026. Grade beams and low-flow walk piers are going in now.

MeetingAug 4, 2026

Riverwalk Planning, Design and Construction Committee — August 4, 2026

Two competing visions for the riverbank near Eagle Street: a naturalized shoreline with native plants (Option A) versus a wider 8-foot concrete walk (Option B). Design isn't budgeted until 2029 and construction until 2031, with updated concepts due in early 2027.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Naperville

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.