Highway 50 shared-use path design costs
Summary
Resident Vernon Air flagged that TWM's design bills for the Highway 50 trail have hit about $75,000 over three months without construction starting. Staff noted a $3 million state grant offsets the project, which will connect Community Park to the RecPlex.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 4, 2026.
Impact analysis
About $75,000 spent on design so far, against a $273,000 engineering agreement offset by a $3 million grant.
Walkers, runners and cyclists who will use the trail between Community Park and the RecPlex.
Taxpayers footing the design bill until construction begins.