Proposed Data Center — 3528 Edgewater Drive
Description
The developer's attorneys formally terminated the purchase agreement for the proposed data center site, officially ending the project.
Impact summary
Residents fear impacts to property values, water, wildlife, and quality of life near McNaughton Park; public meetings are set for Feb 24 and March 24.
Applicant
- Name
- Pekin I Developer LLC
- Address
- 3528 Edgewater Drive, Pekin, IllinoisSee this on the map
At a glance
- Hearings
- 3
- Public comments
- 14
- Total mentions
- 3
Last discussed May 11, 2026.
Meeting timeline (3)
City Council - May 11, 2026
The developer's attorneys formally terminated the purchase agreement for the proposed data center site, officially ending the project.
City Council - Feb 9, 2026
The proposed data center drew nearly unanimous public opposition; no decision was made, and the developer is still responding to the Council's risk contingencies.
City Council - Jan 26, 2026
A proposed data center drew strong public opposition Monday; the council has not voted and says it is still doing due diligence, with a town hall set for March 24.
Related issues (2)
Proposed Data Center
The city is weighing a proposed data center project, with residents asking about the developer, funding, site plans, and long-term impacts. Two town halls — Feb. 24 at the library and March 24 at the high school theater — will let the public weigh in and learn more.
Data Center Project Termination at 3528 Edgewater Drive
The developer formally terminated its purchase agreement for the 321-acre data center site, returning the project's $85,000 deposit to the developer. The city attorney says a lawsuit isn't viable and the city is now free to seek other uses for the land.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Pekin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.