Airport fuel tank construction completion
Summary
New fuel tanks should be running by May or early June, but construction will close part of the ramp and Taxiway Alpha-3 starting mid-March. Pilots will still have fuel and west tie-downs, with only brief fuel outages.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
The removal contract alone is $38,000, plus a $5,000 city deductible if contamination turns up.
Airport users get modern fuel facilities by early summer.
Pilots lose ramp space and two parking positions near the terminal during construction.
Mentions & discussions (4)
Airport Advisory Commission - Oct 27, 2026
The airport's fuel tank construction project was on the agenda for a completion update. This affects fuel availability for pilots and airport operations.
Airport Advisory Commission - May 26, 2026
The airport's new above-ground fuel tanks are almost ready — piping is in and leak-checked, a contractor painting issue has been fixed, and final inspections and testing are about ten working days out.
City Council - Feb 27, 2026
New underground fuel tanks arrive around April 20 after an 8-10 year effort. The airport gets $50K operating and $125K capital transfers from the general fund, contracts out management instead of staffing it, and wants a $25,000 used snow plow.
Airport Advisory Commission - Feb 24, 2026
New fuel tanks should be running by May or early June, but construction will close part of the ramp and Taxiway Alpha-3 starting mid-March. Pilots will still have fuel and west tie-downs, with only brief fuel outages.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Pekin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.