Court Street Stormwater Relocation Project
Summary
The city is funding engineering to relocate the stormwater pond on Court Street as part of the public infrastructure for the one-acre land sale in front of Menards; the buyer, JPG, will perform the physical work at its own expense.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 22, 2026.
Impact analysis
Engineering costs will be borne by the city as part of the development infrastructure commitment.
Commercial development of the Court Street site and stormwater management in the area.
Drivers face day-long closures and a malfunctioning signal at 14th and Court in the meantime.
Mentions & discussions (3)
City Council - Jun 22, 2026
A resident told the council stormwater runoff has been damaging his property for years and asked for ditch maintenance and an on-site meeting with staff.
City Council - May 26, 2026
Big project, big headaches: closures on Court Street between 8th and 10th on Wednesday and Friday from 5 a.m. to 5 p.m., plus frustration over the broken traffic light at 14th and Court. The council funded $150,000 more in stormwater engineering for the Graves development area.
City Council - Jan 26, 2026
The city is funding engineering to relocate the stormwater pond on Court Street as part of the public infrastructure for the one-acre land sale in front of Menards; the buyer, JPG, will perform the physical work at its own expense.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Pekin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.