Medium PriorityInfrastructureopen

Terminal roof replacement at Pekin Municipal Airport

Summary

The airport's terminal roof, with original metal sheeting from the 1960s–70s, is slated for replacement. Core sampling will check for asbestos before bids go out, and the whole project is expected to stay under the State's $150,000 allocation — but it has slipped to Fall 2026.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jan 27, 2026.

Impact analysis

💰Financial impact

Roofing is estimated at about $75,000, with total costs expected under the State's $150,000 allocation.

✅Who benefits

Airport users and staff get a sound terminal roof before the old 1960s–70s sheeting fails.