Four Creeks Wind
Description
A special use permit application to construct and operate up to 113 commercial wind turbines and supporting infrastructure across 27,113 acres.
Impact summary
If approved, this would be one of the largest wind projects in central Illinois, bringing an estimated $1.5 billion in construction, hundreds of jobs, and major school tax revenue — but also 657-foot towers on the horizon for neighbors who didn't sign leases.
Applicant
- Name
- Four Creeks, LLC (Repsol Renewables)
- Address
- Brimfield, Millbrook, Princeville, and Jubilee Townships, Peoria County, IL
At a glance
- Hearings
- 3
- Public comments
- 104
- Total mentions
- 3
Last vote · County Board
A recommendation, not a final decision. The council decides next.
Discussed at 1 meeting in the last 60 days; most recently Nov 5, 2026.
Meeting timeline (3)
County Board - Land Use Committee - Nov 5, 2026
A Special Use Permit for up to 113 wind turbines up to 657 feet tall and 663 MW of capacity across about 27,113 acres. The ZBA recommended denial 4-2, but the Land Use Committee voted to approve with 36 conditions and forward it to the full County Board.
County Board - Nov 5, 2026
A special use permit for up to 113 wind turbines (max 657 feet tall) and 663 MW of capacity, approved with 36 county conditions including 100% decommissioning funding, five-year sound studies, and shadow flicker curtailment.
Zoning Board of Appeals (Special) - Sep 14, 2026
A special use permit request for up to 113 wind turbines (up to 657 feet tall) and 663 megawatts of capacity, plus access roads, collection lines, a substation, and an O&M building. Day one of the hearing covered the developer's case; the ZBA will recommend to the County Board.
Related issues (3)
Four Creeks, LLC zoning petition (ZBA-2026-0037)
A proposal to build up to 113 wind turbines, up to 657 feet tall, across about 27,000 acres of northwest Peoria County — the largest zoning case in county memory. Supporters point to hundreds of construction jobs, $300 million in property taxes (62% to schools), and landowner payments; opponents question grid interconnection, missing application details, and the credibility of the Spanish oil-and-gas parent company Repsol.
Zoning Petitions Review
Four Creeks, LLC has a zoning case before the county, and the Land Use Committee is set to consider it Thursday. What the committee recommends could shape how the affected property can be used.
Four Creeks Wind Energy Road Use Agreement
A developer wants to build up to 113 wind turbines — some 657 feet tall — across about 27,000 acres of farmland in four northern Peoria County townships. Supporters typically point to lease payments and tax revenue; opponents raise concerns about noise, views, and property values. The board's decision would shape the county's landscape and energy future for decades.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Peoria County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.