Summary
Public Works laid out a $47 million five-year plan with $48 million in identified funding: street resurfacing, Willow Road and Hillcrest flood control, the Elmhurst Road culvert, West Camp McDonald stormwater work, water main loops, and a fire department expansion with police lot repaving and security fencing breaking ground in May.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 23, 2026.
Impact analysis
Funded largely by grants, the $20 million road bond referendum, and about $1 million a year in general fund transfers to capital.
Residents through flood control, better roads, sidewalks near schools, and improved water reliability.