Flood Plain Compensatory Storage Reduction
Summary
Prospect Heights years ago tightened its flood compensation requirement to 1.5-to-1; this project asked to go back to the 1.1-to-1 MWRD standard. The city engineer found flooding risk would not be significant at 1.1, and a new ordinance allows case-by-case variations.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 22, 2026.
Impact analysis
Reducing the required compensatory storage ratio from 1.5:1 to 1.1:1 lowers the developer's flood-mitigation excavation and site-work costs.
The developer saves on flood storage work; the city engineer's analysis found flood risk acceptable at the lower ratio.