High PriorityWater Utilitiesopen

Hillcrest Lake Outflow Flood Control Project

Summary

A new outflow pipe will carry Hillcrest Lake overflow north to the creek instead of flooding backyards between Owen Court and Kenilworth, addressing complaints from major 2017-2019 storms. The construction bid of $588,259.70 was awarded, with about 75% paid by a state grant.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Mar 9, 2026.

Impact analysis

💰Financial impact

The city's local share is roughly $150,000-$170,000 after the $420,000 state grant, with 10% contingency added for underground surprises.

✅Who benefits

Residents whose backyards flood from lake overflow during heavy storms.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Prospect Heights

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.