Hillcrest Lake Outflow Flood Control Project
Summary
A new outflow pipe will carry Hillcrest Lake overflow north to the creek instead of flooding backyards between Owen Court and Kenilworth, addressing complaints from major 2017-2019 storms. The construction bid of $588,259.70 was awarded, with about 75% paid by a state grant.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 9, 2026.
Impact analysis
The city's local share is roughly $150,000-$170,000 after the $420,000 state grant, with 10% contingency added for underground surprises.
Residents whose backyards flood from lake overflow during heavy storms.