Willow Trails Stormwater Project Supplemental Cost
Summary
The flood control project hit unexpected costs — asbestos pipes, unmapped water mains, winter cold-patching — adding $192,336. Thanks to a $2.4 million federal grant, the city's share stays under its $800,000 budget at roughly $790,000, and officials say the project remains on track for spring completion.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 8, 2026.
Impact analysis
City's share of the $3.2 million project is expected to land around $790,000 — still under the $800,000 budget.
Plaza businesses, drivers and pedestrians who get flood control and permanent spring repaving.
Taxpayers could face higher project costs unless cost sharing or grants close the gap.
Mentions & discussions (3)
City Council - Jun 8, 2026
Utility relocation delays pushed the $3.2 million flood-control project into winter, adding a $16,000 engineering cost. The city is still under budget thanks to $2.4 million in federal grants.
City Council - Jan 26, 2026
Soft soil is forcing Cook County to require a stronger culvert foundation, which could push the Willow Road project from $600,000 to as much as $1 million. The city, Cook County, and MWRD will meet in February to try to share the extra cost.
City Council - Jan 12, 2026
The flood control project hit unexpected costs — asbestos pipes, unmapped water mains, winter cold-patching — adding $192,336. Thanks to a $2.4 million federal grant, the city's share stays under its $800,000 budget at roughly $790,000, and officials say the project remains on track for spring completion.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Prospect Heights
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.