A deep well drilled in 1964 under the Fairfax Water Tower failed a few weeks ago and needs $434,000 in emergency repairs. It provides radium treatment as part of the village's water supply.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 4, 2026.
Impact analysis
About $434,000, though that's still an estimate.
Everyone who drinks village water — it keeps a key treatment well online.
Mentions & discussions (3)
Village Board — November 4, 2026
Emergency repair work on Village Well #7 was on the consent agenda with bidding requirements waived. Water supply reliability is at stake for residents.
Village Board — September 16, 2026
A deep well drilled in 1964 under the Fairfax Water Tower failed a few weeks ago and needs $434,000 in emergency repairs. It provides radium treatment as part of the village's water supply.
Village Board — June 3, 2026
Trustees approved a $166,500 village-owned watermain extension connecting the Grand Prairie Water Commission's Airport Road main to the village reservoir — one piece of the larger regional water project targeted for around 2030.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Romeoville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.