Roselle · week of November 7, 2026

Council approves Accounts Payable List for November 9, 2026, 4–0

Summarized from the official meeting transcript — every claim links to the moment it was said. How we make this

What changed in Roselle

  • Change Order No. 2 — 2026 Concrete Improvement Program

    5 yes, 0 no

    Cheryl Lenisa (yes), Tom Della Penna (yes), Lee Trejo (yes), Tom Piorkowski (yes), Wayne D. Domke (yes)

    Watch this moment →
  • Accounts Payable List for November 9, 2026

    4 yes, 0 no, 1 abstain

    Cheryl Lenisa (yes), Lee Trejo (yes), Tom Della Penna (yes), Tom Piorkowski (yes), Wayne D. Domke (abstain)

    Watch this moment →
  • Change Order No. 1 — 2026 Storm Sewer Improvement Program

    5 yes, 0 no

    Cheryl Lenisa (yes), Lee Trejo (yes), Tom Della Penna (yes), Tom Piorkowski (yes), Wayne D. Domke (yes)

    Watch this moment →
  • Design engineering agreement — 2027 and 2028 Water Main Improvement Program

    5 yes, 0 no

    Wayne D. Domke (yes), Cheryl Lenisa (yes), Tom Della Penna (yes), Lee Trejo (yes), Tom Piorkowski (yes)

    Watch this moment →
  • Consent agenda: October 26 minutes, 233 E. Maple agreement amendment, and IDOT agreement

    5 yes, 0 no

    Cheryl Lenisa (yes), Tom Della Penna (yes), Wayne D. Domke (yes), Tom Piorkowski (yes), Lee Trejo (yes)

    Watch this moment →
  • Reappointment of Margaret Ross to the Firefighters' Pension Board

    5 yes, 0 no

    Cheryl Lenisa (yes), Lee Trejo (yes), Tom Piorkowski (yes), Wayne D. Domke (yes), Tom Della Penna (yes)

    Watch this moment →
  • 2026 property tax levy resolution

    5 yes, 0 no

    Tom Piorkowski (yes), Lee Trejo (yes), Tom Della Penna (yes), Cheryl Lenisa (yes), Wayne D. Domke (yes)

    Watch this moment →
  • Presentation of Prepared Agenda

    0 yes, 0 no

    Watch this moment →

Also discussed

  • Property tax levy

    The Village adopted its 2026 property tax levy and committed not to exceed the state tax-cap limit for the coming year.

    What it means: Property taxpayers benefit from the board's pledge not to exceed the tax cap.

    Follow this issue →
  • FY 2027 budget deficit and revenue options

    The Village faces an $860,805 general fund deficit for FY 2027. The board chose one-time reserves, a natural gas tax bump, and electric tax transfers instead of a home-rule sales tax increase — but that option may come back next year.

    What it means: The board is closing an $860,805 gap using about $61,000 in one-time reserves, a gas tax increase worth roughly $120,000 a year, and a $430,000 electric tax transfer.

    Follow this issue →
  • Broadband cable franchise build-out

    A resident asked when internet cable work would reach his neighborhood. Multiple companies hold franchise agreements and are working in different areas; staff offered to check the contractor schedule for his address.

    What it means: Residents awaiting broadband service as providers extend cable infrastructure.

    Follow this issue →
  • Updated Wastewater Master Plan

    New facility plans lay out the next 10–20 years of sewer, lift station, and treatment plant work, driven by tightening phosphorus limits (a 0.35 mg/L benchmark by 2040) and aging 1970s–80s infrastructure. The plans position the Village for competitive state EPA loan funding.

    What it means: All residents benefit from reliable sewers and treatment plants that meet future environmental rules.

    Follow this issue →
  • 2026 Water Main and Sanitary Sewer Replacement Project

    The board green-lit small change orders on 2026 concrete and storm sewer contracts and hired engineers to design the 2027–2028 water main replacement program.

    What it means: Adds about $12,500 in construction change orders and $139,300 for water main design engineering.

    Follow this issue →
  • Proposed 'Friends of the Village of Roselle' foundation

    Trustee Domke floated creating a nonprofit foundation so residents and businesses could make tax-deductible donations for things like fireworks and Winterfest. The board asked him to bring back a business plan for 2027.

    What it means: Community event supporters and organizations like RACF, the museum, and library could receive new funding.

    Follow this issue →
  • Water main, concrete, and storm sewer improvements

    The board green-lit small change orders on 2026 concrete and storm sewer contracts and hired engineers to design the 2027–2028 water main replacement program.

    What it means: Adds about $12,500 in construction change orders and $139,300 for water main design engineering.

    Follow this issue →
  • Fiber optic construction moratorium

    A resident asked when internet cable work would reach his neighborhood. Multiple companies hold franchise agreements and are working in different areas; staff offered to check the contractor schedule for his address.

    What it means: Residents awaiting broadband service as providers extend cable infrastructure.

    Follow this issue →
  • FY 2027 Proposed Budget review

    The Village faces an $860,805 general fund deficit for FY 2027. The board chose one-time reserves, a natural gas tax bump, and electric tax transfers instead of a home-rule sales tax increase — but that option may come back next year.

    What it means: The board is closing an $860,805 gap using about $61,000 in one-time reserves, a gas tax increase worth roughly $120,000 a year, and a $430,000 electric tax transfer.

    Follow this issue →

Published by Illinois Record. 1 meeting covered.