Broadband cable franchise build-out
A resident asked when internet cable work would reach his neighborhood. Multiple companies hold franchise agreements and are working in different areas; staff offered to check the contractor schedule for his address.
Updated Wastewater Master Plan
New facility plans lay out the next 10–20 years of sewer, lift station, and treatment plant work, driven by tightening phosphorus limits (a 0.35 mg/L benchmark by 2040) and aging 1970s–80s infrastructure. The plans position the Village for competitive state EPA loan funding.
2026 Water Main and Sanitary Sewer Replacement Project
The board green-lit small change orders on 2026 concrete and storm sewer contracts and hired engineers to design the 2027–2028 water main replacement program.
Water and Sewer Fund Health
DuPage Water Commission rates came in lower than budgeted (about $79,000 in savings), but the village faces unbudgeted IEPA-required reports, a $20,000 drying bed, and a $470,000 water tower rehab project that may stretch into 2027.
2026 Storm Sewer Improvement Program
Stormwater remains the only capital area without a dedicated funding stream. The Seasons Four project near Montrose Markets and the Devlin West design (tied to District 12's Roselle Middle School plans) are priorities, but construction money is still needed.
Lead service line replacement
The village expanded its grant program for replacing lead water lines: full coverage now reaches households up to 150% of the poverty level, with 50% and 25% coverage at 175% and 200%. Few residents have applied so far.