The board approved the Orchard Water Tower contract with Dorner Company, a water valve exercising program, and water meters from Midwest Meter Inc. (with a bid waiver). That's upkeep on the system that supplies your tap water.
At a glance
- Total mentions
- 4
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Nov 16, 2026.
Impact analysis
Contract amounts are included in the $1.76 million expenditure approval; bid waiver means competitive bids were not sought for the meters.
Every household and business connected to village water service.
Mentions & discussions (4)
Village Board — Council — 2026-11-16
The Board is scheduled to approve water meters from Midwest Meter, Inc. and engineering from Gewalt Hamilton Associates for a village-wide meter replacement program. Meter replacements can affect how residents are billed for water.
Committee of the Whole — Committee of the Whole — 2026-11-09
The village was set to buy new water meters from Midwest Meter, Inc. and hire Gewalt Hamilton Associates to manage the replacement program.
Village Board — Council Meeting — 2026-06-15
The board approved the Orchard Water Tower contract with Dorner Company, a water valve exercising program, and water meters from Midwest Meter Inc. (with a bid waiver). That's upkeep on the system that supplies your tap water.
Committee of the Whole — COW — 2026-06-08
Many meters south of Rollins Road predate 1990, and a village-wide replacement plan still lacks funding. Meanwhile staff keep replacing meters and rebuilding pumps at the Orchard Tower and Wood Street stations to avoid failures.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Round Lake Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.