Grand Prairie Water Commission project progress

Summary

The regional water project is moving: designs are 60% to 90% complete and bids are being prepped, but the IDNR denied permits for the Des Plaines River crossing, forcing a hunt for a new location. Village valve stations are 95% done and the corrosion study is nearly finished.