New traffic signal at Wynstone and Route 52
Summary
Pavement markings are done at the Route 52/Wynstone signal; activation of the pedestrian signal awaits IDOT's schedule. Speed tables on Vertin Boulevard are being installed starting this week.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Sep 2, 2026.
Impact analysis
Part of the $1.008 million signalization project, currently 43% complete.
Pedestrians at Route 52/Wynstone and residents of Vertin Boulevard see safety improvements.
Mentions & discussions (4)
Planning & Zoning Commission - Sep 2, 2026
Commissioners raised concerns about fast traffic on Route 52 where The District would access the road, requesting a right-turn lane. A speed-limit cut from 50 to 45 mph is coming, and Wynstone may eventually extend to Black Road.
Village Board - Apr 28, 2026
Pavement markings are done at the Route 52/Wynstone signal; activation of the pedestrian signal awaits IDOT's schedule. Speed tables on Vertin Boulevard are being installed starting this week.
Village Board - Mar 24, 2026
The long-awaited light was turned on the day of the meeting, with good feedback so far. Pavement markings and the pedestrian signal will follow when weather allows.
Village Board - Feb 24, 2026
All traffic signal materials for the Route 52/Wynstone intersection are on site and installation begins in coming weeks, targeting completion by early April, before the YMCA opens. Trustees also noted a recent accident there with no serious injuries.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Shorewood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.