High PriorityRoadsopen

Seil Road bridge replacement and reconstruction

Summary

Rain has slowed the Seil Road bridge project, but the contractor expects to finish the bridge work this month, with road work between the bridge and Route 59 possibly starting before winter.

At a glance

Total mentions
10
Last 30 days
2

Rising — discussed at 3 meetings since Sep 22, 2026, up from 1 in the two months before.

Impact analysis

💰Financial impact

$8.9 million construction bid administered through IDOT.

✅Who benefits

Residents who travel Seil Road daily.

⚠️Who could be affected

Drivers face continued delays while weather stalls the schedule.

Mentions & discussions (10)

MeetingNov 10, 2026

Village Board - Nov 10, 2026

The board approved over $1.5 million in payments for the Seil Road bridge reconstruction (IDOT) and the pumping station and 5-million-gallon reservoir project — major infrastructure work taxpayers are funding through existing project budgets.

MeetingOct 27, 2026

Village Board - Oct 27, 2026

Residents along the south end of the Seil Road project (States Lane to River Bluff) should get their entrances reopened before winter. Bridge beams go in within two to three weeks and asphalt could follow within a week or two.

MeetingSep 22, 2026

Village Board - Sep 22, 2026

Rain has slowed the Seil Road bridge project, but the contractor expects to finish the bridge work this month, with road work between the bridge and Route 59 possibly starting before winter.

MeetingAug 25, 2026

Village Board - Aug 25, 2026

Concrete pours for the Seil Road bridge's north abutment start any day, and road reconstruction between States Lane and the Southwest Frontage Road begins in weeks. Expect major construction activity and some patience required.

MeetingJun 23, 2026

Village Board - Jun 23, 2026

The Seil Road bridge and road project is running a couple of weeks behind schedule while the contractor waits on IDNR and Will County approvals for river access. Demo plans were just approved and work could start within days.

MeetingMay 12, 2026approved

Village Board - May 12, 2026

The village is planning roughly $600,000 in repairs to the Mound Road bridge, starting design now but doing the work only after the Seil Road bridge project is finished.

MeetingMar 24, 2026

Village Board - Mar 24, 2026

The bridge work has started with a full closure. Drivers are testing the barricades and figuring out detours; complaints are coming in but fewer than police expected.

MeetingMar 4, 2026

Planning & Zoning Commission - Mar 4, 2026

Commissioner Cappel reported a recent crash at Seil Road and the SW Frontage Road; staff said they weren't aware of major injuries.

MeetingFeb 17, 2026

Committee of the Whole - Feb 17, 2026

Shorewood is on the hook for 20% of the Seil Road bridge replacement cost plus the full cost of rebuilding the road — just over $6 million total. That's one of the biggest infrastructure hits in the draft budget.

MeetingJan 27, 2026

Village Board - Jan 27, 2026

IDOT awarded the Seil Road bridge job with Austin Tyler as low bidder at $8.9 million. Construction could start in late spring and run 18 months.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Shorewood

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.