MediumDevelopment

YMCA and Lennar construction progress

The YMCA is in its final month of construction with the pool already filled, and Lennar has three houses under roof at Town Center with more foundations going in this week.

3 mentionsLast discussed Oct 13, 2026
MediumDevelopment

Lenny's Gas N Wash PUD Amendment

Gas N Wash wants to build an indoor 20-bay self-serve detailing center with a restaurant on about two acres at River and Jefferson. Trustees pressed the owner on noise from 20 vacuums, a 15-minute time limit, closing at 10 p.m., and extending a berm to protect Hunt Club neighbors — answers expected at the PZC hearing.

2 mentionsLast discussed Oct 7, 2026
MediumDevelopment

Rusty Ridge Animal Center MRI addition

The veterinary clinic is adding an 832-square-foot building to bring its MRI out of a trailer and into the facility. Trustees debated whether to cap the MRI's magnetic field at 1.5 Tesla in the PUD but approved the amendment without that restriction, relying on existing noise and building codes.

4 mentionsLast discussed Sep 22, 2026
MediumDevelopment

Hamptons Modification Requests

The Village was set to discuss modifications requested at the Hamptons development, but the meeting was cancelled because the applicant's representatives couldn't attend. Residents waiting to see or comment on these changes will need to watch for a rescheduled meeting.

1 mentionLast discussed Sep 8, 2026
MediumDevelopment

Shorewood Horizon senior community walking path safety

The stamped asphalt path around the senior living building is cracking and becoming a trip hazard; the board let owners replace it with smooth colored asphalt.

1 mentionLast discussed Aug 11, 2026
MediumDevelopment

The Pointe at Kipling Estates Courtyard Phase

For-sale townhome-style courtyard units near the Kipling clubhouse, starting around $300,000–$350,000, with planned access to Kipling amenities and proximity to a park and Four Seasons Park. Annexation and a PUD process are anticipated.

1 mentionLast discussed Jun 3, 2026
MediumDevelopment

GoPro sports dome annexation compliance

The GoPro sports dome on County Line Road never fully matched its 2020 annexation plan. The board gave it a phased path to compliance through 2028 — roads, grass, soil piles and landscaping — but Trustee Brockman voted no, and a trustee noted the on-site pond is a mess.

1 mentionLast discussed Apr 14, 2026
MediumDevelopment

Shorewood Towne Center II resubdivision

After Lennar built the pond and got the flood map revised by the Army Corps, 23 previously floodplain-limited units can now be platted as part of the 139-unit PUD.

1 mentionLast discussed Mar 10, 2026
MediumDevelopment

Outdoor storage for equipment parts supplier at 500 Earl Road

American United Mechanical Technology wants to store large equipment racks outdoors behind a 10-foot screening fence at the former RR Brink site. Commissioners probed truck traffic and road wear before backing the plan.

1 mentionLast discussed Mar 4, 2026
MediumDevelopment

Clearwave Fiber at 1001 Geneva St

A fiber internet company wants to use the old Schwan's industrial building, including outdoor storage. A neighboring resident spoke in support, and the Commission found no truck-parking concerns.

1 mentionLast discussed Feb 4, 2026
MediumDevelopment

Inka Group trucking facility at 1005 Geneva St

A small trucking company wanted to open a fleet-maintenance facility at the former Ajax Linen site, with strict conditions limiting repairs to its own trucks, indoor work only, and no idling. Despite a 7-0 Planning and Zoning recommendation, the Board rejected it 5-1.

2 mentionsLast discussed Jan 13, 2026